30. 08. 2013. - The contract for the outdoor assembly substation in Algeria

Our company has successfully continued to win major contracts in the international market. So the Algerian GRTE awarded a new contract to Energoinvest as the most successful bidder in the international tender No. 07/2012 KDL.p. The contract relates to:

Lot No. 7, outdoor assembly substation 60/30 kV El Karma 2x40 MVA.

The contract is notified (valjda parafiran ili potpisan – initialled or signed) on 19 August 2013 and one of its original copies was delivered to Energoinvest. The total cost of El Karma substation is approximately 9.6 million EUR. The deadline to construct this facility is 22 months.